Katy ISD Bond 2017 Construction Update

-

$609,204,553 Bond Program

​New Schools

Project Estimated
Project Cost
Anticipated
Start 
Date
​Anticipated Completion Date ​Project
Status
Amy Camp​bell Elementary School
​(​Elementary #41)


2017 Bond Funds

$19,000,000​​

2014 Bond Funds
$5,675,813

November 2016​ July 2018 In Progress  
​Elementary #42

  • Construction Video​ – Coming Soon
  • De​​​sign​ – Coming Soon
  • General Project Info
  • Move-In Photos​ – Coming Soon
  • Photo​ Gallery​ – Coming Soon
$33,021,303 December 2017​ August 2019 In Progress
Elementary #43

  • Construction Video​ – Coming Soon
  • Design​ – Coming Soon
  • General Project Info
  • Move-In Photos – Coming Soon​
  • P​hot​o Gallery​ – Coming Soon
$35,675​,464 September 2018 July 2020

​Junior High #16

​$54,920,468 ​March 2017  August 2019 In Progress
Junior High #17

  • Construction Video – Coming Soon
  • D​esign​ – Coming Soon
  • General Project Info
  • Move-In Photos​ – Coming Soon
  • Photo G​allery​ – Coming Soon
​$65,611,222 August 2019 August 2021  ​

High School #9

$206,074,464 March 2017 July 2020

​​Property Acquisition

  • Constru​ction V​i​d​eo – Coming Soon
  • ​​De​sign
  • General Project Info
  • Photo ​​Gallery – Coming Soon
  • Move-I​n Photos​ – Coming Soon
​$18,000,000 Ongoing​ Ongoing​

In Progress

​​​Infrastructure

  • Construct​ion Video – Coming Soon
  • Design​ – Coming Soon
  • General Project Info​
  • Move-In Photos – Coming Soon
  • Photo ​Gallery – Coming Soon
$16,375,000​ April  2018​ ​Ongoing

In Progress​​
​​

Total                                        $448,677,921

""​​​​​

Comprehensive Renovation   ​

​Project ​Estimated
Project Cost
Anticipated Start Date ​Anticipated Completion Date ​Project
Status
Fielder Elementary Renovation

  • Construction Video – Coming Soon
  • General Project Info
  • Move-In Photos – Coming Soon
  • Photo Gallery​ – Coming Soon
$20,854,960 ​ January 2018 August 2019 In progress

Total                                               $20,854,960

""

Component Replacements

​Project

​Estimated
Project Cost

Anticipated Start Date

​Anticipated Completion Date

​Project
Status

​​Mayde Creek Elementary & Mayde Creek Junior High Foundation Repair Work

​$1,198,274 ​Dec​ember 2017 July 2018 In Progress
​​Chiller Replacements

​$11,223,000  January 2018​  July 2019​ In Progress
​Boiler Replacements

$847,000 January 2018​ July 2018​ In Progress
​​Roof Replacements

​$7,983,720 January 2018  July 2020​ In Progress
​​Interior & Exterior Lighting Retrofits

​$4,785,000  January 2018​  July 2020​ In Progress
​Athletic Surface Replacements

​$5,578,650 January 2018  July 2020​ In Progress
Natatorium Component Replacements 

​$1,019,000  January 2018​  July 2019​ In Progress
Cinco Ranch Junior High & Cinco Ranch High School Kitchen Renovations and Campus Floral Coolers

​$4,815,102 October 2018​ July 2019​ Planning
​Flooring Replacements

​Videos

​$6,489,948 January 2018  July 2020​ In Progress
​Scoreboard & Sound System Replacements

​$925,000  January 2018​  July 2020​ In Progress
​Controls Replacement

​$7,119,200 ​ January 2018 ​ July 2020 In Progress

Total                                               $51,983,894

"" ​

School Expansions​

Project ​Estimated
Project Cost
Anticipated
Start Date
​Anticipated Completion Date ​Project
Status
Katy High School Career & Technical Education Renovation

  • Construction Video – Coming Soon
  • General Project Info
  • Move-In Photos – Coming Soon
  • Photo Gallery  – Coming Soon
​ $8,083,643 January 2018 August 2019 In Progress
​Raines High School/BTP

  • Construction Video – Comin​g Soon
  • General Project Info
  • Move-In Photos – Coming Soon
  • Photo Gallery – Coming Soon
$7,330,567 September 2019 July 2021

Planning

Total                                               $15,414,210

""

​ Safety & Security Improvements

Project ​Estimated
Project Cost
Anticipated Start Date ​Anticipated Completion Date ​Project
Status
Outdoor Learning Center Renovations

$6,875,030 July 2018 March 2020 Planning
​Emergency Generator  & Fire Alarm Replacements

​$3,775,000 ​January 2018 July 2020 In Progress
​Elevator Refurbishments

$334,000 ​ January 2018 July 2018 In Progress
​Security Fencing & Gates

$721,406 January 2018 July 2019 In Progress
​Police Software & Computers

​$605,000 January 2018 August 2018 In Progress
Security System Retrofits

​$1,400,000 January 2018​ December 2020​ In Progress
​Access Controls

​$3,000,000 January 2018​ December 2020​ In Progress

Total                                               $16,710,436

""

Technology

​Project ​Estimated
Project Cost
Anticipated Start Date ​Anticipated Completion Date ​Project
Status
Campus Retrofit: 2018-2019

Elementary: Stephens; Sundown; WoodCreek; Davidson; Randolph

$3,467,282 ​ August 2018 ​ July 2019 In Progress
​Campus Retrofit: 2019-2020

Elementary: Pattison, Holland, Morton Ranch, Alexander; Kilpatrick, McRoberts

Junior High: WoodCreek, Cardiff, West Memorial, Katy, Mayde Creek, Morton Ranch

High School: Opportunity Awareness Center Raines, Miller Career and Technology Center, Cinco Ranch

​$12,081,511 ​August 2019 ​July 2020

Planning

​Campus Retrofit: 2020

Elementary: Franz, Exley, Mayde Creek

Junior High: Beckendorff

High School: Mayde Creek, Morton Ranch

​$7,038,201 ​August 2020 ​December 2020 Planning
​Replacement of Network Access Switches

​$3,621,200 ​June 2018 ​July 2019 Planning
​Upgrade of Wireless Access Points & Controllers

​$2,204,500 ​June 2018 ​July 2019 Planning
​Network Security Infrastructure

​$1,280,000 ​June 2018 ​December 2020 Planning
​Server Lifecycle & Growth

​$2,000,000 ​January 2018 ​December 2020 In Progress

Total                                               $31,692,694

""

Other

Project ​Estimated
Project Cost
Anticipated Start Date ​Anticipated Completion Date ​Project
Status
​​Underground Fuel Tanks

$4,904,233 ​ January 2018 ​ February 2019 In Progress
​Buses

$17,591,205 ​January 2018 ​December 2020 In Progress
​Portables

​Video

​$1,375,000 ​January 2018 ​July

2018

In Progress

Total                                               $23,870,438

""

​ ​​​​​​​​​​